Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 15th -16th floors. This includes the installation of facade elements on balconies. The facade is being winterized. 2. Installation of drywall frames, the 4th -6th floors. 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. – Tiling on the 3rd floor. – Finishing works on the 13th floor. 4. Diamond core drilling for engineering openings on the 15th –16th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems – Assembling and installation of water supply manifolds 15th -17th floors. – Hot and cold water supply risers are being installed. 6. Waterproofing of the balconies, the 5th floor. 7. Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges, 8th–9th floors Formwork and reinforcement for ledges designed to support stained-glass installations. 9. Masonry works, the 20th floor. 10. Floor screeding.