Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 17th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. 2. Glazing of stained glass windows, the 14th – 15th floors. Glass installation. 3. Installation of cast-in ledges, the 9th floor. The formwork is being installed, concrete is poured, and compacted. Once the concrete has reached the required strength, the formwork is dismantled, and glazing installation begins. 4. Installation of drywall frames for internal partitions. Thus provides a strong and stable foundation for wall construction. Enclosing niches on the 3rd floor and profile installation on the 11th-20th floors are in progress. 5. Installation of decorative columns on the 10th floor and cladding of balcony columns on the 11th -20th floors. 6. Plumbing and sewer system installation. Installation of stormwater drainage systems on the 15th – 20th floors. Installation of sewage systems on the 15th – 16th floors. Installation of water supply risers on the 3rd floor. 7. Mockup construction on the 3rd and 13th floors. Finishing works. 8. Masonry work on the 20th floor. Laying ceramic blocks in strict adherence to technological requirements. 9. Floor screed installation on balconies, the 2nd – 3rd floors. 10. Ventilation installation on the 3rd floor. Installation of air ducts. 11. Balcony waterproofing on the 12th -13th floors. 12. Diamond core drilling for engineering openings on the 2nd floor. Marking and drilling of precise openings for the installation of utilities in the future hotel. 13. Suspended ceiling installation on balconies, 2nd floor.