Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 2nd, 3rd, 6th floors. This includes the installation of facade elements on balconies. The facade is being winterized. 2. Installation of drywall frames, the 18th , 20th floors. – for internal partitions on the 15th -18th floors. – for balcony ceiling, on the 4th floor 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. – Tiling on the balconies of the 13th floor. 4. Diamond core drilling for engineering openings on the 5th – 6th, 18th – 20th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel – 14 engineering openings. 5. Installation of utilities systems – Horizontal water supply piping across units, the 20th floor – Stormwater drainage, steel bracket installation. 6. Construction of concrete ledges, 8th–9th floors Formwork and reinforcement for ledges designed to support stained-glass installations. 7. Installation of water supply and sewage systems, 20th floor Installation of water supply risers. 8. Waterproofing balconies on the 4th floor. 9. Pouring for steel railing posts on balconies, 6th floor. 10. Fabrication and installation of steel arches On balconies of the 9th floor. 11. Installation of suspended ceilings On balconies of the 4th floor. 12. Installation of the fire protection system Initial layout of the fire protection system across floors.