Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 3rd, 11th – 15th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames for internal partitions, on the 19th floor. Thus provides a strong and stable foundation for wall construction. 3. Mockup construction on the 3rd floor. Plumbing and painting are in progress on the 3rd floor. 4. Diamond core drilling for engineering openings on the 4th, 20th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel – 14 engineering openings. 5. Ceramic block installation, on the 20th floor. Laying ceramic blocks in accordance with the technology. 6. Cast-in ledges installation, on the 20th floor. It is necessary for stained glass installation. 7. Waterproofing of the balconies on the 12th – 13th floors. 9. Installation of the ceiling on the balconies. 10. Laying of tiles.