Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 3rd, 13th, 19th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. – Installation of internal partitions, the 6th – 9th floors. – Cladding of ledges, the 6th–9th floors. 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. – Tiling on the 3rd floor. 4. Diamond core drilling for engineering openings on the 13th , 15th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Assembling and installation of water supply manifolds on the 16th -17th floors. – Hot and cold water supply risers are being installed, the 15th – 16th floors. 6. Waterproofing of the balconies. On the 7th – 8th floors. 7. Marking Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges, 8th –9th floors Formwork and reinforcement for ledges designed to support stained-glass installations. 9. Floor screeding, the 12th floor. The floor screeding is being installed. 10. Elevator shafts are being installed. 11. Masonry works, the 20th floor. The ceramic block installation.