Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 3rd, 4th, 7th , 8th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. – Installation of internal partitions. – Cladding of ledges, the 11th –14th floors. 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. 4. Diamond core drilling for engineering openings on the 8th – 10th , 16th ,17th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Assembling and installation of water supply manifolds, the 6th – 9th floors. – Hot and cold water supply risers are being installed, the 6th -9th floors. – Cladding of the stormwater drainage duct, 11th floor. 6. Waterproofing of the balconies. On the 4th , 7th , 17th floors. 7. Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges, 3rd -4th floors Formwork and reinforcement for ledges designed to support stained-glass installations. 9. Floor screeding, the 11th floor. The floor screeding is being installed. 10. Elevator shafts are being installed, the 2nd floor. – Priming of elevator’s shafts 11. Masonry works, the2nd , 20th floors. Ceramic block installation.