Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 3rd, 4th, 7th , 8th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. – Installation of internal partitions, the 4th – 8th floors. – Cladding of ledges, the 6th –9th floors. 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. 4. Diamond core drilling for engineering openings on the 3rd , 7th , 11th , 12th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Assembling and installation of water supply manifolds, the 11th – 14th floors. – Hot and cold water supply risers are being installed, the 11th -13th floors. – Cladding of the stormwater drainage duct, 2nd–7th floors. 6. Waterproofing of the balconies. On the 14th – 15th floors. 7. Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges, 4th , 17th – 18th floors Formwork and reinforcement for ledges designed to support stained-glass installations. 9. Floor screeding, the 12th floor. The floor screeding is being installed. 10. Elevator shafts are being installed, the 2nd floor. – Ceramic block installation. – Priming of shafts 11. Masonry works, the 20th floor. Ceramic block installation.