Wyndham Grand Batumi Gonio. Family Club. Block A 1. Facade works. Insulation of the facade. 2. Installation of suspended ceilings. Arrangement of ceiling framework on balconies. 3. Manufacturing of metal arches for installation on balconies. 4. Installation of engineering systems, 2nd floor. Arrangement of the frame of storm water drainage boxes. 5. Work on the floor screed. Block B 1. Plastering works. Plastering of walls on balconies, 5th floor. 2. Masonry works, 5th floor. Ceramoblock masonry. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Facade works.
Insulation of the facade.

2. Installation of suspended ceilings.
Arrangement of ceiling framework on balconies.

3. Manufacturing of metal arches for installation on balconies.

4. Installation of engineering systems, 2nd floor.
Arrangement of the frame of storm water drainage boxes.

5. Work on the floor screed.

Block B
1. Plastering works.
Plastering of walls on balconies, 5th floor.

2. Masonry works, 5th floor.
Ceramoblock masonry.