Wyndham Grand Batumi Gonio. Family Club. Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. 2. Arrangement of suspended ceilings, 1 floor. Arrangement of ceiling framework on balconies. 3. Floor screed works. On the balconies, 3rd floor. Block B 1. Plastering works. Plastering of walls on balconies, 4th floor. 2. drilling of engineering holes in the elevator shafts. 3. Installation of engineering systems, 2 floor. Installation of storm water drainage. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Installation of stained glass windows.
Installation of stained glass structures and glass.

2. Arrangement of suspended ceilings, 1 floor.
Arrangement of ceiling framework on balconies.

3. Floor screed works.
On the balconies, 3rd floor.

Block B
1. Plastering works.
Plastering of walls on balconies, 4th floor.

2. drilling of engineering holes in the elevator shafts.

3. Installation of engineering systems, 2 floor.
Installation of storm water drainage.