Wyndham Grand Batumi Gonio. Family Club. Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. 2. Facade arrangement. Works on the device of facade insulation on balconies. 3. Arrangement of suspended ceilings. Arrangement of the ceiling framework on the balconies. 4. Works in the workshop. Manufacturing of metal arches. Block B 1. plastering works. — Plastering of walls on balconies, 4th floor. — Plastering of the roof parapet, ventilation shafts. 2. Masonry works, 5th floor. Ceramoblock masonry. 3. Installation of engineering systems. Installation of storm water drainage. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Installation of stained glass windows.
Installation of stained glass structures and glass.

2. Facade arrangement.
Works on the device of facade insulation on balconies.

3. Arrangement of suspended ceilings.
Arrangement of the ceiling framework on the balconies.

4. Works in the workshop.
Manufacturing of metal arches.

Block B
1. plastering works.
— Plastering of walls on balconies, 4th floor.
— Plastering of the roof parapet, ventilation shafts.

2. Masonry works, 5th floor.
Ceramoblock masonry.

3. Installation of engineering systems.
Installation of storm water drainage.