Wyndham Grand Batumi Gonio. Family Club. Block A 1. Plastering work. Plastering of slopes, 2nd floor. 2. Facade work. — Facade and slope cladding with clinker tiles. — Plastering of the facade. — Facade insulation. 3. Installation of plasterboard frame. Covering of ceiling frame. 4. Waterproofing work. Preparatory work for waterproofing terraces. Block B. 1. Masonry work, 5th floor. Laying ceramic blocks. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Plastering work.
Plastering of slopes, 2nd floor.

2. Facade work.
— Facade and slope cladding with clinker tiles.
— Plastering of the facade.
— Facade insulation.

3. Installation of plasterboard frame.
Covering of ceiling frame.

4. Waterproofing work.
Preparatory work for waterproofing terraces.

Block B.
1. Masonry work, 5th floor.
Laying ceramic blocks.