Wyndham Grand Batumi Gonio. Family Club Block A 1. Plastering Works Plastering of interior walls, 2nd, 3rd floors. 2. Installation of Glazing Structures Installation of stained-glass windows. 3. Works in Elevator Shafts Plastering works. Block masonry. 4. Masonry Works Masonry of ceramic block on the roof. 5. Waterproofing Works Preparation for waterproofing balconies, application of coating waterproofing. 6. Installation of Parapet Lintel on the Roof. 7. Installation of Drywall Frame Installation of guiding frames for drywall partitions. Block B 1. Diamond Drilling of Engineering Openings For stormwater drainage system installation. - European Village

Wyndham Grand Batumi Gonio. Family Club

Block A
1. Plastering Works
Plastering of interior walls, 2nd, 3rd floors.

2. Installation of Glazing Structures
Installation of stained-glass windows.

3. Works in Elevator Shafts
Plastering works.
Block masonry.

4. Masonry Works
Masonry of ceramic block on the roof.

5. Waterproofing Works
Preparation for waterproofing balconies, application of coating waterproofing.

6. Installation of Parapet Lintel on the Roof.

7. Installation of Drywall Frame
Installation of guiding frames for drywall partitions.

Block B
1. Diamond Drilling of Engineering Openings
For stormwater drainage system installation.