Wyndham Grand Batumi Gonio. Family Club. Building A 1. Formwork is installed, concrete is poured and compacted. Upon completion of the concrete strength, the formwork is dismantled and the stained glass windows are installed. 2. Plastering of parapets, on the roof Includes the application of several layers of plaster to ensure a tight fit waterproofing. 3. Ceramoblock masonry, 3rd floor Building B 1. Ceramoblock masonry, 2nd floor on balconies Check all dimensions and adherence to process standards. 2. Column reinforcement works, 5th floor To increase the strength and stability of the columns, allowing them to withstand loads.