Wyndham Grand Batumi Gonio. Family Club. Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd, 5th floors. — Concreting the ledges on the balconies, the 3rd, 5th floors. — Installation of reinforced frame for the balcony ledges, the 5th floor. 2. Plastering on the 1st- 4th floors. Plastering of inner walls. 3. Plumbing. Installation of stormwater drainage system on the balconies. 4. Masonry works, the roof. Ceramic block installation. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Building A
1. Installation of cast-in ledges on the balconies.
— The formwork installation for the balcony ledges on the 3rd, 5th floors.
— Concreting the ledges on the balconies, the 3rd, 5th floors.
— Installation of reinforced frame for the balcony ledges, the 5th floor.

2. Plastering on the 1st- 4th floors.
Plastering of inner walls.

3. Plumbing.
Installation of stormwater drainage system on the balconies.

4. Masonry works, the roof.
Ceramic block installation.