Wyndham Grand Batumi Gonio. Family Club.
Building A
1. Installation of
— The formwork installation for the ledges on the balconies, the 5th floor.
— The installation of the reinforced frame for the balcony ledges.
— The formwork installation for the ledges on the balconies, the 3rd floor.
2. Plastering on the 3rd floor.
Plastering of inner walls.
Building B.
1. Masonry works, the 5th floor.
Ceramic block installation.