Wyndham Grand Batumi Gonio. Family Club.
Building A
1. Installation of
The ledges are being formworked and reinforced for stained glass windows to be installed.
2. Plastering, the 1st, 4th floors.
3. Installation of drywall frames, the 1st floor.
Installation of guides for drywall partition frames.
4. Diamond core drilling for engineering openings.
Marking and drilling of precise openings for the installation of utilities in the future hotel.
Building B.
1. Masonry work, the 4th floor.
Ceramic block installation on the balconies.