Wyndham Grand Batumi Gonio. Family Club.Building A 1. Installation of drywall profiles, 2nd – 3rd floors. To create a strong and stable base that forms the walls. 2. Facade works. The facade works were started. 3. Insulation of the balconies. Preparation for waterproofing installation. Building B. 1. Masonry of exterior walls, the 4th floor. Laying ceramic blocks in accordance with the technology. 2. Formwork installation. Installation of formwork to create the necessary shape for concrete pouring and structural formation. The earthworks for site landscaping are underway.