Wyndham Grand Batumi Gonio. Family Club.Building A 1. Installation of drywall profiles, 2nd – 3rd floors. To create a strong and stable base that forms the walls. 2. Facade works. The facade works were started. Building B. 1. Ceramic block installation, the 4th – 5th floors. Laying ceramic blocks in accordance with the technology. 2. Formwork installation. Installation of formwork to create the necessary shape for concrete pouring and structural formation. The earthworks for site landscaping are in progress.