Wyndham Grand Batumi Gonio. Family Club. Building A 1. Installation of drywall profiles, 3rd – 4th floors. Ongoing works. It creates a strong and stable base that forms the walls. 2. Insulation of the balconies. Preparation for waterproofing installation. 3. Ceramic block installation on the roof. The ceramic blocks are installed following the technology Building B. 1. Masonry of exterior walls, the 4th floor. Laying ceramic blocks in accordance with the technology. 2. Formwork installation, the 5th floor. The formwork is installed to create the necessary shape for concrete pouring and structural formation. The earthworks for site landscaping are underway.