Wyndham Grand Batumi Gonio. Family Club. Building A 1. Installation of drywall profiles, on the 4th floor. Ongoing works. It creates a strong and stable base that forms the walls. 2. Insulation of the balconies. Preparation for waterproofing installation. 3. Ceramic block installation on the roof. The ceramic blocks are being installed following the technology. Building B. 1. Ceramic block installation, on the 4th floor. Laying ceramic blocks in accordance with the technology. 2. Formwork installation, on the 5th floor. The formwork is installed to create the necessary shape for concrete pouring and structural formation. The earthworks for site landscaping are in progress.