Wyndham Grand Batumi Gonio. Family Club. Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete hardens, the formwork is removed, and the stained glass windows are installed. 2. Diamond drilling for engineering openings for downpipes. The layout and drilling are underway, necessary for future hotel utility installations. 3. Plastering of roof parapets. Building B 1. Beam Reinforcement. The reinforcement is essential to ensure the strength and load-bearing capacity of beams. It prevents deformation and cracking, ensuring the durability of the structure.