Wyndham Grand Batumi Gonio. Riviera 1. Block A, B. Plastering Works Plastering of interior walls. 2. Block A. Mock-up Works Electrical installation. 3. Block A. Installation of Engineering Systems Installation of the sewage and ventilation systems. 4. Block A. Installation of Glazing Structures Slope finishing and stained-glass installation. 5. Block A. Masonry Works Masonry of external walls, technical floor. 6. Block B. Installation of Drywall Frame Installation of guiding frames for drywall partitions. 7. Block A. Floor Screed Installation on Terraces Works on the 1st floor. - European Village

Wyndham Grand Batumi Gonio. Riviera

1. Block A, B. Plastering Works
Plastering of interior walls.

2. Block A. Mock-up Works
Electrical installation.

3. Block A. Installation of Engineering Systems
Installation of the sewage and ventilation systems.

4. Block A. Installation of Glazing Structures
Slope finishing and stained-glass installation.

5. Block A. Masonry Works
Masonry of external walls, technical floor.

6. Block B. Installation of Drywall Frame
Installation of guiding frames for drywall partitions.

7. Block A. Floor Screed Installation on Terraces
Works on the 1st floor.