Wyndham Grand Batumi Gonio. Riviera.
1. Plastering.
— Plastering of inner walls in Blocks C, B.
2. Block B. Ongoing formwork installation for staircases.
It helps to create the exact shape and geometry of the staircase, to maintain the concrete until it hardens, to ensure surface quality and structural safety.
3. Block C. Installation of drywall frames.
Installation of guides for drywall partition frames.
4. Block E. Façade works.
Facade winterization.
5. Block A. Installation of steel chimney framing on the terrace.