Wyndham Grand Batumi Gonio. Villas.1. Completion of column formwork removal, Villas 8, 9. Removal of formwork after concrete hardening to complete the structure and prepare for the next construction phase. 2. Waterproofing of floor slab underlay, Villas 12, 14, 15. Necessary to protect the structure from moisture penetration from the ground, preventing concrete deterioration and ensuring floor durability. Work has been fully completed on Villa 14. 3. Continuation of formwork installation for ceiling slabs, Villas 7, 10. Installation of formwork to create the shape of the slab, necessary for pouring concrete and forming its structure. 4. Installation of safety bars, Villa 7. Safety bars have been installed on the 2nd floor. 5. Uploading of ceramic blocks. 3 batches of the material have been accepted.