Wyndham Grand Batumi Gonio. Villas. 1. Continuation of staircase formwork installation, Villa 5. The formwork is installed to shape the staircase, enabling concrete pouring and the formation of its structure. 2. Continuation of slab formwork installation, Villas 7, 10. The formwork is installed to shape the slab, allowing for concrete pouring and the formation of its structure. 3. Backfilling of inner part of the foundation, Villa 16. It enhances thermal insulation and evenly distributes the load on the foundation, preventing deformation. 4. Column concreting, Villas 8 and 9. It ensures the strength and stability of vertical structures, forming a reliable foundation for the entire building framework. 5. Formwork removal from the slab, Villa 6. Removal of formwork after the concrete has set, completing the structure and preparing it for the next stage of construction. 6. Continuation of fence formwork installation and extension of the perimeter fence.