Wyndham Grand Batumi Gonio. Villas.1. Formwork installation for slabs, Villas 7-10 Installation of formwork to shape the slabs, essential for pouring concrete and forming the structure. 2. Floor slab insulation, Villas 12, 15 Enhances the building’s energy efficiency. The work has been completed on Villa 12. 3. Floor slab reinforcement, Villa 12 Reinforcement of the floor slab strengthens the structure, preventing deformation. 4. Insulation of external foundation walls, Villa 12 The work has been completed. 5. Backfilling external foundation walls, Villas 5, 6 Improves thermal insulation and evenly distributes the load on the foundation, preventing deformation. 6. Concrete pouring for under-slab preparation on Villa 16, floor slab on Villa 14, and fence foundation Concrete pouring has been completed.