Wyndham Grand Batumi Gonio. Villas. 1. Masonry works. Ceramoblock masonry exterior walls, villa 1, 3, 5, 6. 2. Formwork for the monolithic staircase from 1 to 2 floors, villas 14, 15, 16. Installation of formwork to create the mold, which is necessary to pour the concrete and form the structure. 3. Reinforcement work of the monolithic staircase from 1st to 2nd floor, villa 14, 15. Provides strength and stability to the structure, preventing deformation and increasing the durability of the building. 4. Concreting works — floor slab of the 2nd floor, villa 10, N11. — monolithic staircase from the 1st to the 2nd floor, villa 10, 11, 12, 13. — columns of the II floor, villa 12, 13, 14. Ensures the strength and stability of the structures, forming a solid foundation for the entire building structure. - European Village

Wyndham Grand Batumi Gonio. Villas.

1. Masonry works.
Ceramoblock masonry exterior walls, villa 1, 3, 5, 6.

2. Formwork for the monolithic staircase from 1 to 2 floors, villas 14, 15, 16.
Installation of formwork to create the mold, which is necessary to pour the concrete and form the structure.

3. Reinforcement work of the monolithic staircase from 1st to 2nd floor, villa 14, 15.
Provides strength and stability to the structure, preventing deformation and increasing the durability of the building.

4. Concreting works
— floor slab of the 2nd floor, villa 10, N11.
— monolithic staircase from the 1st to the 2nd floor, villa 10, 11, 12, 13.
— columns of the II floor, villa 12, 13, 14.

Ensures the strength and stability of the structures, forming a solid foundation for the entire building structure.